Electrical Panel Upgrade Cost Calculator

Circuits in the panel
24 circuits
Service size
How much is being replaced
Where it goes
Your ZIP code

Showing the national average. Enter your ZIP code for local cost estimates.

Low $2,625
Typical $3,175
High $3,950

National average

Where these figures come from
  • Electrical contractors, United States: $43.61/hour, August 2026 (BLS CES CES2023821003)
  • 200 amp load center and main breaker: $280.00 per panel (price recorded October 2026, not index-adjusted)
  • Circuit breaker, per circuit: $18.00 per circuit (price recorded October 2026, not index-adjusted)
  • Service cable, meter socket, grounding and conduit: $420.00 per service (price recorded October 2026, not index-adjusted)

Electrical Panel Upgrade costs $2,625 to $3,950 for a typical 24 circuits job in 2026, against a national benchmark of $3,175. Labor runs 15.2 crew hours at $43.61 an hour. Enter a ZIP code to apply that area's measured wages for this work and its regional price level.

What makes up the price

Labor $928 15.2 hours at $43.61/hour, 40% burden, 1.00x regional
200 amp load center and main breaker $280 1 panel at $280.00 each
Circuit breaker, per circuit $432 24 circuit at $18.00 each
Service cable, meter socket, grounding and conduit $420 1 service at $420.00 each
Permit, inspection and utility coordination $300
Contractor overhead and profit $826 35% applied to the work above
Typical total $3,175 $2,625 to $3,950 depending on contractor

Cost by size

National averages, before any local adjustment. Computed from the same model as the calculator above, so the two always agree.

Circuits in the panel Circuits Typical Range
14 circuits 14 $2,700 $2,200 to $3,350
20 circuits 20 $3,000 $2,450 to $3,700
24 circuits 24 $3,175 $2,625 to $3,950
32 circuits 32 $3,575 $2,925 to $4,425
40 circuits 40 $3,975 $3,250 to $4,925

Why two quotes differ by thousands

Almost always because they are not quoting the same job, and the difference has a name that rarely appears on either quote.

Panel only

The existing service cable, mast and meter socket stay. The old load center comes off the wall, a new one goes on, and every circuit is moved across. Around $2,300 for a typical house.

This is only possible if the existing service entrance is already rated for the new panel and is in good condition — which, if the panel is old enough to be replaced, it often is not.

Panel and service entrance

Everything from the weatherhead in: new mast, new meter socket, new service cable, new grounding. Around $3,175, and the usual answer when a 100 amp service becomes a 200 amp one.

Plus utility-side work

If the service drop from the pole, or the underground lateral, has to be upsized, the utility does that part on its own schedule and the electrician works around it. Around $4,300, and several weeks longer.

Ask any electrician which of these three they are quoting. It is the single most useful question on this page.

The amperage is a red herring

A 200 amp load center is under $300 at a big-box store. A 100 amp one is $160. The $140 between them is a rounding error on a $3,000 job.

What actually costs money:

So going from 100 amp to 200 amp costs almost nothing extra in equipment. If you are replacing a panel at all, there is rarely a good reason to put back a 100 amp service.

When you actually need more capacity

A 100 amp service is genuinely adequate for a house with gas heat, gas water heating and a gas range. It becomes inadequate when things start getting added:

A load calculation is the honest way to answer this, and any electrician proposing a service upgrade should be willing to do one. It is arithmetic on the actual connected load rather than a rule of thumb, and it sometimes shows that an existing 100 amp service is fine and a $3,000 job is not needed.

Panels that are a safety problem, not a capacity one

For some readers this is not an upgrade decision. If your panel is one of these, replacement is a safety matter and the capacity question is secondary.

Insurers increasingly refuse to cover houses with FPE or Zinsco panels, and home inspectors flag them at sale. If you have one, that is the reason to do this job and the budget question is how, not whether.

Aluminum branch wiring

Separately: houses wired with aluminum branch circuits between about 1965 and 1973 have a connection problem at devices rather than a panel problem. A new panel does not fix it. The accepted remedies are copper pigtails with approved connectors or a rewire, and anybody quoting a panel as the solution has not understood the issue.

What the day looks like

Questions worth asking

Common questions

How much does it cost to upgrade an electrical panel?

Around $3,175 for a 200 amp panel and a new service entrance on a 24 circuit house, with most jobs falling between $2,625 and $3,950. Replacing only the panel and keeping the existing service entrance is closer to $2,300, and work that needs the utility to upsize the service drop is around $4,300.

Why do electrical panel quotes vary so much?

Because they are quoting different scopes under the same name. A panel swap keeps the existing mast, meter socket and service cable; a service upgrade replaces all of it; and a utility-side upgrade adds a new service drop on the utility's schedule. Those three are roughly $2,300, $3,175 and $4,300 for the same house. Asking which one is being quoted is the most useful question you can ask.

Does upgrading from 100 amp to 200 amp cost much more?

Barely anything in equipment — a 200 amp load center is under $300 against $160 for a 100 amp. The cost is in the circuits, the service entrance and the permit, which are the same either way. If you are replacing a panel at all, there is rarely a good reason to put back a 100 amp service.

Do I need a 200 amp service?

Not necessarily. A 100 amp service is genuinely adequate for a house with gas heat, gas water heating and a gas range. It becomes inadequate when an EV charger, a heat pump, an electric range or an addition gets added. A load calculation answers this properly, and any electrician proposing an upgrade should be willing to do one — it sometimes shows the existing service is fine.

Is a Federal Pacific or Zinsco panel dangerous?

Both have documented histories of breakers failing to trip under overload, and both are commonly flagged by home inspectors and increasingly refused by insurers. If you have one, replacement is a safety decision rather than a capacity one, and the question is how to budget for it rather than whether to do it.

How long does a panel upgrade take?

About 15 hours of electrician time for a 24 circuit house, which is usually one long day on site. The power is off for four to eight hours of that. The longer part is scheduling: the utility has to pull and reset the meter, and an inspector has to release the work before it goes back.

Do I need a permit to replace an electrical panel?

Yes, everywhere, and the inspection is not optional — the utility will not reset the meter without it. A permit is typically $150 to $400. Unpermitted service work is both a safety problem and the kind of thing that stops a house sale.

Why is moving the panel so expensive?

Because every circuit in the house has to be extended to reach the new position, usually with a junction box left at the old one. It adds around 40% to the job. If the reason for moving it is cosmetic, it is worth asking whether it is worth that.

What are AFCI and GFCI breakers and do I need them?

Arc-fault and ground-fault breakers, which current code requires on most living-area and wet-location circuits. They cost $45 to $60 each against about $10 for a standard breaker, so on a 24 circuit panel the difference is several hundred dollars. A quote that is notably cheaper than another may be assuming standard breakers where code now requires these.

Will a new panel fix aluminum wiring?

No. Houses wired with aluminum branch circuits between about 1965 and 1973 have a problem at the connections to switches and outlets, not at the panel. The accepted remedies are copper pigtails with approved connectors, or a rewire. Anybody quoting a panel replacement as the fix for aluminum wiring has not understood the issue.

Where these numbers come from

Nothing here is copied from a contractor directory. Labor is priced from what the trades are actually paid, materials from published producer prices, and both are adjusted to your area using federal cost-of-living data.