Concrete Slab Cost Calculator

Slab area
400 sq ft
Thickness and reinforcement
What is there now
Finish
Your ZIP code

Showing the national average. Enter your ZIP code for local cost estimates.

Low $3,200
Typical $3,900
High $4,850

National average

Where these figures come from
  • Poured concrete foundation and structure contractors, United States: $38.54/hour, August 2026 (BLS CES CES2023811003)
  • Ready-mix concrete, delivered: $170.00 per cubic yard (price recorded October 2026, not index-adjusted)
  • Crushed stone base, delivered: $45.00 per cubic yard (price recorded October 2026, not index-adjusted)
  • Welded wire reinforcing mesh: $0.25 per sq ft of slab (price recorded October 2026, not index-adjusted)
  • Forms, stakes, joint filler and curing compound: $0.45 per sq ft of slab (price recorded October 2026, not index-adjusted)

Concrete Slab costs $3,200 to $4,850 for a typical 400 sq ft job in 2026, against a national benchmark of $3,900. Labor runs 25.2 crew hours at $38.54 an hour. Enter a ZIP code to apply that area's measured wages for this work and its regional price level.

What makes up the price

Labor $1,360 25.2 hours at $38.54/hour, 40% burden, 1.00x regional
Ready-mix concrete, delivered $836 4.9 cubic yard at $170.00 each
Crushed stone base, delivered $221 4.9 cubic yard at $45.00 each
Welded wire reinforcing mesh $100 400 sq ft of slab at $0.25 each
Forms, stakes, joint filler and curing compound $180 400 sq ft of slab at $0.45 each
Hauling the excavated soil $200
Contractor overhead and profit $1,014 35% applied to the work above
Typical total $3,900 $3,200 to $4,850 depending on contractor

Cost by size

National averages, before any local adjustment. Computed from the same model as the calculator above, so the two always agree.

Slab area Sq ft Typical Range
220 sq ft 220 $2,525 $2,075 to $3,150
320 sq ft 320 $3,300 $2,700 to $4,100
400 sq ft 400 $3,900 $3,200 to $4,850
540 sq ft 540 $4,975 $4,075 to $6,175
680 sq ft 680 $6,050 $4,975 to $7,500

The sheet of plastic that decides how the slab behaves

If anything is going on top of this slab — a building, a floor covering, stored tools, a workshop — the most important thing in the quote is a vapor barrier: 10 to 15 mil polyethylene laid directly under the concrete, lapped six inches at the seams and taped, and run up the edge of the form.

Concrete is porous. Ground moisture moves up through a slab continuously, by capillary action, for as long as the slab exists. There is no curing period after which it stops. Without a barrier you get, in rough order of appearance:

The barrier costs somewhere around $0.10 to $0.20 a square foot. Retrofitting one is impossible — the only fix after the fact is a topical moisture-blocking epoxy at several dollars a foot, and it is a partial fix.

One detail that gets argued about: the poly goes directly under the slab, not under the gravel with a layer of sand on top. The sand-cushion method was standard decades ago and is now understood to create a reservoir that holds water against the slab. Directly under the concrete is the current guidance.

Ask the question plainly: is there a vapor barrier, what thickness, and is it under the concrete or under the gravel?

The edge, if walls are landing on it

A slab sitting in the open can be a uniform four inches. A slab carrying a structure cannot — the perimeter has to take the weight of the walls and roof and get below the frost line, or the building moves with the seasons.

Three arrangements, and which one you need is a code question for your jurisdiction:

Frost depth varies from nothing in the south to 48 inches or more across the northern tier. A garage on a floating slab in Minnesota is a building that lifts an inch every January and comes back down in April, and it will show in the walls within a few years.

This page prices a uniform slab. A thickened edge or separate footings is extra concrete and extra excavation, and a quote that includes them will be above the figure above — ask for it as a separate line so you can see it.

The bolts have to go in wet

If a wall plate is fastening to this slab, anchor bolts get set into the concrete while it is still plastic — pushed in, to the right depth, at the spacing the plans or code call for, within an inch or two of where the plate actually needs them.

The alternative is drilling and epoxying or expansion-bolting afterwards, which works but is slower, more expensive, and relies on the installer not hitting rebar. The common failure is not that they were forgotten; it is that nobody knew where the walls were going, so they were set by guesswork and half of them end up in the wrong place.

Have the building layout settled before the pour, not after. This is the single cheapest hour of planning on the whole project.

Why a small pad costs so much per square foot

For a 400 sq ft slab at four inches with mesh, at $3,900:

Concrete, about 4.9 cubic yards around $825
Base stone, mesh, forms and curing around $500
Labor, about 25 crew hours around $1,350
Hauling the excavated soil around $200
Overhead and margin the balance

Now scale it down. A 120 sq ft shed pad needs a quarter of the concrete but the crew still mobilizes, excavates, forms, sets a barrier, pours, finishes, and comes back to cut joints. The total lands near $1,775 — about $14.80 a square foot against $9.75 for the 400, and $8.50 for a 1,000 sq ft slab.

This is why published figures of $4 to $7 a square foot for a shed slab do not describe a contractor job. At 120 sq ft the ready-mix alone is $315 to $405 once the short-load fee is in, and the base, mesh, poly and forms take it past $500 before anybody has been paid. A $500 to $800 shed pad is a concrete order and your own weekend.

Two ways to make a small slab cost less per foot:

Thickness, honestly

The steel matters more than the inch. A four inch slab with #3 rebar at 18 inches on center resists cracking at two to three times the load of the same slab with mesh alone, so if you are choosing between an extra inch and better reinforcement, take the reinforcement.

Specify 4,000 psi for anything exterior or unheated, with air entrainment where it freezes. Three thousand psi is a thin spec for a slab that has to take vehicles or freeze-thaw cycling, and the difference in the concrete bill is small.

Slope, flatness and drains

A slab under a building is not a patio and the rules invert:

The curing timetable

Keep the surface damp for the first few days in hot, dry weather or confirm that a curing compound went on. Concrete does not dry, it reacts with water, and a slab whose surface loses its water too early ends up with a weak, dusty top layer — which on a garage floor is the layer you are going to be standing on and parking on.

Questions worth asking

Common questions

How much does a concrete slab cost?

Around $3,900 for a 400 sq ft slab at four inches with wire mesh, with most jobs that size falling between $3,200 and $4,850 — about $9.75 per square foot. Five inches with a rebar grid adds roughly $625 and six inches about $1,400. Size moves the per-foot figure a lot: a 120 sq ft pad works out near $14.80 a square foot and a 1,000 sq ft slab near $8.50, because the crew mobilizes, forms, pours and returns to cut joints either way.

How much does a 24x24 garage slab cost?

About $7,250 at six inches with a #4 rebar grid, or $6,150 at five inches with a #3 grid — 576 square feet either way. Six inches is the right spec if a lift is going in or the subgrade is poor; five is enough for ordinary cars and light trucks. Neither figure includes a thickened edge or separate footings for the walls, which a detached garage will need and which should appear as its own line on a quote.

Does a concrete slab need a vapor barrier?

Yes, if anything is going on top of it — a building, a floor covering, stored tools, a workshop. Ground moisture moves up through concrete continuously by capillary action and never stops, so without a barrier the floor stays damp, flooring adhesive releases, metal rusts and an enclosed building grows mold. Use 10 to 15 mil polyethylene laid directly under the concrete, lapped six inches and taped, at roughly $0.10 to $0.20 a square foot. It cannot be retrofitted.

Should the vapor barrier go under the gravel or under the slab?

Directly under the slab. Putting poly under the gravel with a sand cushion on top was standard practice decades ago and is now understood to create a reservoir that holds water against the concrete. Current guidance is the barrier immediately beneath the concrete, on top of the compacted base. It is worth asking the question specifically, because the old method is still used by crews who learned it that way.

How thick should a concrete slab be?

Four inches with welded wire mesh for a shed, an equipment pad or a base under something light. Five inches with a #3 rebar grid for a garage floor or a workshop — anything cars drive onto. Six inches with a #4 grid for a garage with a lift, a barn, or farm equipment. The steel matters more than the inch: a four inch slab with #3 rebar at 18 inches on center resists cracking at two to three times the load of the same slab with mesh alone.

Does a slab for a garage need footings?

Almost always something more than a uniform slab, and which arrangement depends on your climate and code. A monolithic slab — the floor and a thickened perimeter beam 12 to 16 inches deep poured at once — is the usual answer for a detached garage in a mild climate. Where the ground freezes hard, separate footings below frost depth are required, and frost depth runs from nothing in the south to 48 inches or more across the northern tier. A garage on a floating slab in a cold climate lifts every winter and it shows in the walls within a few years.

Why is a small concrete slab so expensive per square foot?

Because almost none of the cost scales with area. A 120 sq ft shed pad uses a quarter of the concrete of a 400 sq ft slab, but the crew still mobilizes, excavates, forms, lays the barrier and steel, pours, finishes and comes back to cut joints. The total lands near $1,775, or about $14.80 a square foot against $9.75 for the 400. Published figures of $4 to $7 a square foot for a shed slab describe a materials order and your own labor — at that size the ready-mix alone is $315 to $405 once the short-load fee is in.

How can I make a small slab cheaper?

Two things work. Combine it with other concrete work so one mobilization and one delivery covers both — a shed pad poured the same day as a patio or walkway can come in 30% below its standalone price. And consider making it slightly bigger: the step from 120 to 200 square feet adds much less than the per-square-foot figure suggests, because nearly all of the increase is concrete rather than labor.

Do anchor bolts go in before or after the pour?

Into the wet concrete, pushed in to the right depth at the spacing the plans or code require. The alternative — drilling and epoxying or expansion-bolting afterwards — works but is slower, more expensive and depends on the installer missing the rebar. The common failure is not forgetting them; it is setting them before anybody knew where the walls were going. Have the building layout final before the truck arrives.

What psi concrete should a slab be?

Four thousand psi for anything exterior or unheated, with air entrainment where the ground freezes. Three thousand psi is a thin spec for a slab that takes vehicles or freeze-thaw cycling, and the difference in the concrete bill is small enough that there is no good reason to economize there. Air entrainment is the part people skip and it is what stops the surface spalling off after a few winters.

Which way should a garage floor slope?

Toward the door, at about an eighth of an inch per foot — enough that meltwater and washdown leave, shallow enough that nothing rolls on its own. A shed or equipment pad can be dead level and usually should be. If a floor drain is involved, the slope has to be set toward it from every direction, which is real work and belongs on the quote as such; many jurisdictions also require an oil separator before a garage drain can connect to anything.

How long before I can build on a new slab?

Walk on it after 24 to 48 hours, frame a light structure on it after 7 days, and drive a car on it after 7 — but keep anything heavy off for the full 28 days. Epoxy coatings and most sealers also want 28 days, plus a moisture test. Keep the surface damp for the first few days in hot weather or confirm that a curing compound went on, because a slab that loses its surface water early ends up with a weak, dusty top layer, and on a garage floor that is the layer you park on.

Where these numbers come from

Nothing here is copied from a contractor directory. Labor is priced from what the trades are actually paid, materials from published producer prices, and both are adjusted to your area using federal cost-of-living data.